Flooring Tile Replacement at VA Benefits Administration

  • Location: St. Petersburg, Fl
  • Size: 4,700 sf
  • Completed: 2015
  • Duration: 14 Days

About the project

This project consisted of removing 4700 sf of flooring and replacing with ceramic tile. This project took place in a fully operational 3 story building and work was performed on all 3 floors. There was a 30 day completion time from the notice to proceed. S.C. Barker Construction completed the project in 14 days by work both day and night hours.

Because of the confidential nature of this project, no pictures can be displayed.

more projects

    Contact Us

    Let's get to Work!